Week 35 – House Envelope Starts

We are now at the point where the building envelope is being applied, and you really get a sense of the various masses of the house.

img_2228-1

The mason blocks are being installed to create the firebox for the fireplace. Here are views from outside and inside.

img_2229-1img_2231-1

From the upper terrace you really get a sense of the final form of the house.img_2235-1

Here is a view of the upper deck looking to the master. They have finally built it out enough that you can walk around on the second floor.

img_2236-1

Here is a view from the upstairs master looking out to the upper terrace.

img_2244-1

This is the upstairs master bath. The shower is on the left and the tub on the right.

img_2238-1

Here is the view from the upstairs room that faces the street. You feel like you are in the trees.

img_2242-1

It’s nice to see so much progress!