Sound baffles were installed in the ceilings and some interior walls.
Crews were also onsite working on the exterior windows. Now that all the sound baffles are installed, drywall installation can start next week.
Sound baffles were installed in the ceilings and some interior walls.
Crews were also onsite working on the exterior windows. Now that all the sound baffles are installed, drywall installation can start next week.
Insulation inspection passed so drywall is next on the list.
Drywall was installed in the garage so that insulation could be sprayed in behind it.
All the rooms have giant piles ready to go.
All the various inspections have been completed and passed so we can finally move forward again. This week the insulation has sprayed in all the walls.
Drywall should be next for the interiors and the outside stucco and brick should start soon as well.