Week 108 – Steel Work

The steel work has started in the house for both the interior and exterior. On the inside, the fireplace wrapping is installed.

img_2360

The staircase railing has also started.

img_2363

On the exterior, the planters and trellis installing on the roof top deck has also started.

img_2366img_2368

In addition, lots of other general progress. The garage door has been installed.

img_2306

The footing for the staircase leading up to the front door has also started.

img_2307

We should be tracking for completion no later than end of April. We can’t wait to move in!

Week 106 – Bathroom Glass

The upper part of the driveway has cured and looks great.

img_2276

The wood is being installed over the fireplace.

img_2279

All the glass has been installed in the bathrooms.

img_2277img_2283img_2281img_2282img_2284

The stove finally arrived has been installed.

img_2280

It also looks like the garage door has been installed but since it was left open I didn’t want to try closing it in case it wasn’t final yet.

The wood floors are also being prepped for finishing so that will start next week as well.

Week 105 – Appliances

We have been in India for the past few weeks so it was fun to see all the progress made while out of the country.

We arrived today to find the driveway pour started.

img_2146

After navigating around pour, we found all the steel planters installed in the auto-court.

The front door hardware has been installed.

img_2156

The wallpaper has been applied in the powder room.

Kitchen appliances have been installed with the exception of the stove which is currently lost in transit somewhere.

img_2153img_2154

Mirrors have been installed in the bathrooms.

img_2155

The outdoor kitchen appliances have also been installed.

img_2152

Things are progressing nicely and we will hopefully be moving soon.

Week 43 – Fireplace!

It’s been a few weeks since the last post since work slowed down for the holidays and freezing temperatures.

A visit to the house today showed work continuing with all the plumbing and electrical. We also weren’t expecting to have the gas fireplace roughed in.

img_0133

The waterproof membrane has been installed on the deck outside the upstairs master bedroom.

img_0135

Now that the holiday season is over, we expect work to pick up again. Next meeting is with the audio visual contractor to discuss speaker and data drops throughout the house.

Week 25 – Hurricane Harvey

Hurricane Harvey hit the Texas coast this weekend and while Austin is well out of the main path, we’ve received lots of rains with periods of high gusty winds. I drove to the lot to see if we had any downed trees and luckily everything looked good.

The dry creek bed was flowing with water but wasn’t as high and fast as I thought it might be.

img_1671

The top of the lot looked great.img_1672

Some of our neighbors across the street were not so lucky.

img_1679img_1678

We are forecasted to have rain through Wednesday but the storm continues to weaken so hopefully the worst of the rain and wind is over.

Week 9 – Walls getting closer

It appears the rain last week prevented the walls from being poured. There is now a large trench from the back of the lot which I’m assuming is there to help the water drain. 

Here is the north wall with the water proofing and drainage system. 
Here is the west wall with the final form on meaning the steel was inspected. This will be the storage room foundation that ties into the retaining wall. The trench leads up to this area so I’m assuming this back area was too wet to get formed up for the pour. Another shot of the west wall. Shot of trench from storage area looking toward the front of the lot.