Since the weather is so hot, a sprinkler system was setup to help the concrete cure properly and evenly.
Since the weather is so hot, a sprinkler system was setup to help the concrete cure properly and evenly.
After lots of delay due to weather, the foundation finally got poured today. Due to space constrictions on the top of the site, the concrete had to be pumped up in two stages. Here is a video that shows the top pump truck and the line pipe that goes down the drive to another pump truck where the concrete was initially loaded.
The whole process took about 160 cubic yards of concrete and started at 6:00am. When we went back after lunch, the crew was wrapping up the garage and car port area. Here are a few shots of the finished product.
This was a major milestone and we are happy to have it finally done.
We are nearing the end of the site work before the foundation is poured early next week. The cardboard formwork is in and the steel is installed over it.
There are still a few more sections to wrap up. This is the guest suite that needs to be completed, but the beam work steel is in place and that’s the most time consuming. The horizontal slab steel goes in quickly.
By the end of next week, we should have the concrete poured and then the framing can start.
Work continues on the foundation now that the plumbing is inspected. I took a few photos but it is hard to tell a lot of difference but I decided to at least write a post to document another week.
Steel work begun.
Large pile of cardboard forms for the foundation at the base of the site.
We are back from a week in Orlando over the 4th of July holiday, and we visited the site this morning with the builder.
The good news is the plumbing is complete and inspected. Now that inspection has passed they can start tying in the rebar. Here is a shot from the upper terrace.
Some random shot of the plumbing work.
All the cardboard void forms are also onsite in preparation for the foundation pour. There is a pile up in the storage area and another large one at the bottom of the property.
They are working this weekend and hopefully will get to a point of pouring the foundation at the end of next week.