Week 109 – More Steel and Irrigation

The terrace is pretty much done and the steel bases for the railing are installed.

img_2500img_2501

All the structural steel for the floating steps for the front door entry are in place and the rest of it will be formed and poured early next week. It will be so nice to finally have steps.

img_2564

In solar news, the city passed our system and the meter has been installed. It is already pretty cool to see how our system is performing.

img_2568

The main irrigation lines are also installed allowing us to start landscaping.

Things should be wrapping up in the next month and we may move into this house yet.

Week 24 – Steel Framing

It has been a few weeks since my last post since the concrete needed time to cure before any further work could be done.

In the mean time, the site has been cleaned to remove all the debris from the pour and form work, and the steel beams for the walls have been welded into place.

img_1648img_1653img_1647

The remaining beams and trusses are being fabricated now and should be done later this week or early next week.

Week 20 – Final site prep

We are nearing the end of the site work before the foundation is poured early next week. The cardboard formwork is in and the steel is installed over it.

img_1527

There are still a few more sections to wrap up. This is the guest suite that needs to be completed, but the beam work steel is in place and that’s the most time consuming. The horizontal slab steel goes in quickly.

img_1529

By the end of next week, we should have the concrete poured and then the framing can start.