Week 24 – Steel Framing

It has been a few weeks since my last post since the concrete needed time to cure before any further work could be done.

In the mean time, the site has been cleaned to remove all the debris from the pour and form work, and the steel beams for the walls have been welded into place.


The remaining beams and trusses are being fabricated now and should be done later this week or early next week.

Week 20 – Final site prep

We are nearing the end of the site work before the foundation is poured early next week. The cardboard formwork is in and the steel is installed over it.


There are still a few more sections to wrap up. This is the guest suite that needs to be completed, but the beam work steel is in place and that’s the most time consuming. The horizontal slab steel goes in quickly.


By the end of next week, we should have the concrete poured and then the framing can start.