The terrace is pretty much done and the steel bases for the railing are installed.
All the structural steel for the floating steps for the front door entry are in place and the rest of it will be formed and poured early next week. It will be so nice to finally have steps.
In solar news, the city passed our system and the meter has been installed. It is already pretty cool to see how our system is performing.
The main irrigation lines are also installed allowing us to start landscaping.
Things should be wrapping up in the next month and we may move into this house yet.