The interior continued to be prepped for paint as the drywall was finished off.
The steel support for the outdoor patio screen was also installed.
The interior continued to be prepped for paint as the drywall was finished off.
The steel support for the outdoor patio screen was also installed.
The metal roof is on the main structure and it looks great.
On the interior, tape and floating has started on drywall.
The stucco painting has been delayed since the original colors picked didn’t quite look right. Some new samples are going to be painted and hopefully get started next week.
Drywall is almost done and the interior “cleaned” to get up most of the drywall dust and debris off the ground.
The exterior brick on the back end of the house and screen in porch is almost wrapped up.
If the weather holds, exterior stucco painting and roof installation will start next week.
Since a crew was working on Saturday, I did a quick trip back this morning. The downstairs master is finished with initial drywall.
Once thing I really like about the design are the baseboards. They are integrated with the drywall so it is a single plane all the way from the ceiling to the floor.
After a week on vacation, we came back to see lots of progress on both the exterior and interior. The stucco went up very quickly and they are almost done.
Drywall also started and there was a crew continue installation this morning when we stopped by.
With the drywall going up, you really get a sense of the finished room. We are looking forward to what the next week brings.