Week 118 – Certificate of Occupancy

So after a very long process, we got the certificate of occupancy on Wednesday which means we can technically move in although in reality that is still a few weeks away.

We walked the house with the builder today and put stickers on all the areas that needed touch up paint. There is also still a lot of exterior work to be done in the landscaping but the interior is complete.

Speaking of exterior, the parking near the street has been completed and looks great.

img_3078

The upper deck has all the trim now for safety.

img_3082

All the entry planters are in and getting filled with dirt in prep for planting.

img_2994

Hopefully we will be 100% setting by end of July and can throw one hell of a house warming party.

Week 116 – Front Planters

The steel for the planters around the front steps are going in. In addition to looking good, they are necessary for safety so there is less than a three foot drop around the stairs.

img_2978img_2969img_2970img_2976

The barn door to the storage room have been painted.

img_2971

The window tinting has been applied to key windows in the master baths.

img_2974img_2973

A mirror has been added to the upstairs master closet.

img_2975