Week 72 – Wood Siding

The vertical wood siding on the front of the house started this week.

img_0739

The brick work around the entry and guest house is essentially finished.

img_0733img_0734

The work has moved around to the patio and backyard area.

img_0738img_0737

On the interior, the trim work around all the windows and doors is almost wrapped up which will allow the drywall work to start.

img_0736img_0735

Lots of good progress on the exterior this week and the stucco should start next week as well.