Week 7 – House Renderings

I went by the site on Saturday and not a lot of additional work as been done since the footing were poured. Most likely, the concrete needed to cure before they could do additional work. Fun Fact: Concrete doesn’t “dry”; it’s actually an exothermic reaction between the water and cement that causes it to get hard. That architectural engineering degree from UT finally has paid off!

So while there will most likely be work done during the week, here are some additional photos of the house as seen from the street.

Matt Fajkus MF Architecture Balcones Rendering 1 with watermarkMatt Fajkus MF Architecture Balcones Rendering 2 with watermark

Here is a photo of the original house.

22251106233_5d18b92bca_o

One of main design considerations for this project was to respect the original footprint and incorporate some of the design elements from the original house. MF Architecture has done a fantastic job taking our requirements for our new house while respecting the original house and site location.

Week 6 – Retaining Wall Steel

The rain has stopped and work is progressing again. When I arrived on Saturday, I was greeted by this sign.

IMG_1156

I also noticed we had a new water meter box since our original one was crushed by the rig used to drive in the piles.

IMG_1157

At the top of the site, all the structural steel for the retaining walls was almost complete.

fullsizeoutput_514afullsizeoutput_514c

These will be some pretty beefy retaining walls since they are right up against our neighbors property line as well as along the back of the lot. There was a crew there finishing up all the steel, and they are on track to pour them on Monday. If I’m able, I may try and swing by and get some video of the pump truck pouring the footings.

Week 5 – So much mud…

We’ve had rain for the past two weekends, and the property is a muddy mess. The site of the house is primarily clay which made walking up the hill to get some pictures a slippery adventure. We had so much mud on the bottom of our shoes that we had to take them off to drive home.

It looks like they finished excavating the dirt up to our property line along the north edge of the property and on the west edge where the garage with roof top deck will eventually go with access to the upper tier of the yard.

IMG_1147IMG_1148IMG_1149

Luckily, the ten day forecast shows no rain and temperatures in the 70’s so hopefully it will dry out the site and allow work to prepare for the foundation pour. Once the concrete is on the ground, rain won’t be as limiting a factor to make progress.