Week 109 – More Steel and Irrigation

The terrace is pretty much done and the steel bases for the railing are installed.

img_2500img_2501

All the structural steel for the floating steps for the front door entry are in place and the rest of it will be formed and poured early next week. It will be so nice to finally have steps.

img_2564

In solar news, the city passed our system and the meter has been installed. It is already pretty cool to see how our system is performing.

img_2568

The main irrigation lines are also installed allowing us to start landscaping.

Things should be wrapping up in the next month and we may move into this house yet.

Week 108 – Steel Work

The steel work has started in the house for both the interior and exterior. On the inside, the fireplace wrapping is installed.

img_2360

The staircase railing has also started.

img_2363

On the exterior, the planters and trellis installing on the roof top deck has also started.

img_2366img_2368

In addition, lots of other general progress. The garage door has been installed.

img_2306

The footing for the staircase leading up to the front door has also started.

img_2307

We should be tracking for completion no later than end of April. We can’t wait to move in!

Week 106 – Bathroom Glass

The upper part of the driveway has cured and looks great.

img_2276

The wood is being installed over the fireplace.

img_2279

All the glass has been installed in the bathrooms.

img_2277img_2283img_2281img_2282img_2284

The stove finally arrived has been installed.

img_2280

It also looks like the garage door has been installed but since it was left open I didn’t want to try closing it in case it wasn’t final yet.

The wood floors are also being prepped for finishing so that will start next week as well.