Week 108 – Steel Work

The steel work has started in the house for both the interior and exterior. On the inside, the fireplace wrapping is installed.

img_2360

The staircase railing has also started.

img_2363

On the exterior, the planters and trellis installing on the roof top deck has also started.

img_2366img_2368

In addition, lots of other general progress. The garage door has been installed.

img_2306

The footing for the staircase leading up to the front door has also started.

img_2307

We should be tracking for completion no later than end of April. We can’t wait to move in!

Week 106 – Bathroom Glass

The upper part of the driveway has cured and looks great.

img_2276

The wood is being installed over the fireplace.

img_2279

All the glass has been installed in the bathrooms.

img_2277img_2283img_2281img_2282img_2284

The stove finally arrived has been installed.

img_2280

It also looks like the garage door has been installed but since it was left open I didn’t want to try closing it in case it wasn’t final yet.

The wood floors are also being prepped for finishing so that will start next week as well.