Week 118 – Certificate of Occupancy

So after a very long process, we got the certificate of occupancy on Wednesday which means we can technically move in although in reality that is still a few weeks away.

We walked the house with the builder today and put stickers on all the areas that needed touch up paint. There is also still a lot of exterior work to be done in the landscaping but the interior is complete.

Speaking of exterior, the parking near the street has been completed and looks great.

img_3078

The upper deck has all the trim now for safety.

img_3082

All the entry planters are in and getting filled with dirt in prep for planting.

img_2994

Hopefully we will be 100% setting by end of July and can throw one hell of a house warming party.

Week 116 – Front Planters

The steel for the planters around the front steps are going in. In addition to looking good, they are necessary for safety so there is less than a three foot drop around the stairs.

img_2978img_2969img_2970img_2976

The barn door to the storage room have been painted.

img_2971

The window tinting has been applied to key windows in the master baths.

img_2974img_2973

A mirror has been added to the upstairs master closet.

img_2975

Week 114 – We have a bridge!

After almost two months of non-stop rain, the weather finally cooperated and the bridge over the creek bed was finally poured. Here is the finished forms waiting on the concrete to show up.

img_2893img_2896

Pour has started.

img_2897

Finishing up.

img_2898img_2904

It is such a relief to get this done. It was causing access issues to the house to finish up the final interior and exterior items.

The bridge didn’t cause all work to cease. The steel work painting continued.

img_2894img_2895

The upstairs deck was completed including the stairs down to the upper landing area.

img_2900

Landscaping work should start next week now that trucks have access. The interior AV work also continues to get wifi, cameras, and sound systems integrated.

Week 113 – Rain Rain Go Away

The rain has really been slowing down progress on the exterior items. Some progress has been made on the bridge but it is slow going.

img_2816

The floating steps look great and are almost done.

img_2809

Fence work continues.

img_2812

On the inside, we have mirrors in the powder and guest room.

img_2810img_2811

The deck railing continues and is about half way done.

img_2805

Smarter Homes has started all the AV work.

img_2807

I’m keeping my fingers crossed that the bridge can be finished up this week in between the rain which is in the forecast for at least the next week.

Week 112 – Steps and Stairs

We’ve had a lot of rain in the past two weeks that has slowed down the new bridge over the dry creek. It is finally getting formed up and will hopefully get poured next week.

Luckily it hasn’t slowed down the floating front steps.

img_2743

The staircase railing wood has been added and it really looks amazing.

img_2746img_2745

The vent hood cover was finally installed and was really the last item in the kitchen remaining.

img_2747

The sliding barn doors to the storage area has also been installed.

img_2744

Landscaping will also start next week depending on the weather. More rain is in the forecast so we will be fighting that as we try and get this house finished.

Week 110 – Rain

After  a long stretch of dry weather, Austin had a large amount of rain which has put a damper on the new bridge. This is a video just after the rain storm. You can see the water flowing quickly in the creek bed.

This is a few days later. The water is not as high but still flowing.

img_2634

The install for the upper deck has started and is almost complete.

img_2639img_2643

On the interior, installation of the wood on the staircase has begun. The wood and steel combination really looks great.

img_2655img_2656img_2657

We have more rain in the forecast today but hopefully less than half and inch and it is supposed to be a fast moving storm. We need it to dry out to get this bridge complete.