After  a long stretch of dry weather, Austin had a large amount of rain which has put a damper on the new bridge. This is a video just after the rain storm. You can see the water flowing quickly in the creek bed.

This is a few days later. The water is not as high but still flowing.

img_2634

The install for the upper deck has started and is almost complete.

img_2639img_2643

On the interior, installation of the wood on the staircase has begun. The wood and steel combination really looks great.

img_2655img_2656img_2657

We have more rain in the forecast today but hopefully less than half and inch and it is supposed to be a fast moving storm. We need it to dry out to get this bridge complete.