Austin is about to get 3-4 inches of rain today so I ran by the house at lunch to take some photos since it is very difficult to get into the house after a heavy rain with all the clay making the uphill drive way very slick.
The pads for the AC units have been poured and you can even see some of the exterior light sconces have been installed.

They are also preparing an area on the outside of the flex room so people exiting have a small landing area instead of just lawn.
The metal trellis between the main house and guest house has been completed. There is a solid piece of metal between the houses for rain protection but then it is open after that.

The plumber has also started installing fixtures where the tile work is complete. Here is Akash’s room with the shower/tub fixtures installed.

There were also a lot of little finishes like electrical sockets and light switches being installed everywhere. Depending on how much rain, I may try and make it out Sunday depending on how muddy things still are.