Week 97 – Tile and Floor Progress

Slowly but surely, the hardwood floors and bathroom tile work continues.

The upstairs master is very close to completion.

img_1745

The hardwood floor installation upstairs has also started.

img_1742img_1743img_1744

The limestone outdoor patio is compete and has been grouted.

img_1741

The limestone at the front door entry way is also started.

img_1739

I’m hopeful that all the tile and floor work will be done by next week!

 

Week 96 – Floors, Tile, and More!

Hardwood floors are mostly installed in the downstair areas. Sanding and staining will happen near the very end of the project.

img_1664img_1665

The limestone lueders are also being installed in the screened patio area.

img_1666

Tile work also started in the upstairs master. I’m really excited to see how these turn out.

img_1667

They also started the cap work on the exposed concrete on the exterior of the house. The original plan was board formed concrete, but the conditions on the day of the pour (100+ degrees) made it difficult to achieve. So we are going for a smooth finish and a lot of it will be hidden by dirt and plantings anyway.

img_1668

Week 94 – Updates before the rain

Austin is about to get 3-4 inches of rain today so I ran by the house at lunch to take some photos since it is very difficult to get into the house after a heavy rain with all the clay making the uphill drive way very slick.

The pads for the AC units have been poured and you can even see some of the exterior light sconces have been installed.

img_1606

They are also preparing an area on the outside of the flex room so people exiting have a small landing area instead of just lawn.img_1605

The metal trellis between the main house and guest house has been completed. There is a solid piece of metal between the houses for rain protection but then it is open after that.

img_1602

The plumber has also started installing fixtures where the tile work is complete. Here is Akash’s room with the shower/tub fixtures installed.

img_1603

There were also a lot of little finishes like electrical sockets and light switches being installed everywhere. Depending on how much rain, I may try and make it out Sunday depending on how muddy things still are.

Week 94 -Tile and Fans

Tiling work continues in the guest house. We went with a concrete tile in a starburst pattern which looks great.

img_1540img_1541

The downstairs master has the infinity drain installed and the tile work is done around the toilet room.

img_1550img_1546

Speaking of toilets, we’ve got lots in boxes!

img_1547

Fans have also been installed in rooms.

img_1545img_1544

I remembered to take a picture of the installed solar panels and all the electrical panels on the outside of the house.

img_1542img_1549

We are hoping they will start the tile work on the upstairs master this week because we really want to see the tile on the wall.