Hardwood floors are mostly installed in the downstair areas. Sanding and staining will happen near the very end of the project.
The limestone lueders are also being installed in the screened patio area.
Tile work also started in the upstairs master. I’m really excited to see how these turn out.
They also started the cap work on the exposed concrete on the exterior of the house. The original plan was board formed concrete, but the conditions on the day of the pour (100+ degrees) made it difficult to achieve. So we are going for a smooth finish and a lot of it will be hidden by dirt and plantings anyway.