Week 103 – Into the Home Stretch

We can finally see the light at the end of the tunnel at least for the interior. Cleanup has started in prep to finish both the concrete and hardwood floors.

The fireplace hearth was poured.

img_2049

We also have our permanent electric meter installed and the solar will be hooked in shortly so we can start getting credit from the panels.

img_2050

The guest bath tile is finished and will be grouted early next week.

img_2051img_2052

The cork floor was also installed the kitchen but is currently covered so no picture of that yet.

Next week, the driveway will hopefully get started as well as the installation of the steel planters in the auto-court.

Week 98 – Lots of little things

Lots of incremental progress at the house. The kitchen backsplash had grout applied.

img_1801

The upstairs master bathroom tile is down and waiting on grout.

img_1804

Here is Gitanjali and our builder picking grout colors.img_1805

Hardwood floors is pretty much done. Here is the upstairs master closet.

img_1806

Upstairs master bedroom.img_1807

The outdoor kitchen had the black granite counter top applied with matching sink.

img_1802img_1803

If it ever stops raining long enough for the soil to dry out, the black granite backsplash piece will also be installed.

The next two weeks should get all the floors finished along with the staircase including the cork in the kitchen. We should also get final electrical inspection so we can turn on power to the house and get heat and AC working.

Week 97 – Happy New Year!

It’s 2019 and progress marches on. We are in the home stretch and will hopefully be complete in the next 2-3 months.

Upstairs master tile is complete and waiting for grout.

img_1785

Hardwood floor is done except for the upstairs master due to the tile work. Here is Akash’s room.

img_1775

Here is the upstairs landing area.img_1779img_1786

If it ever stops raining long enough so the ground can dry out, they can start the auto-court pavers which would really help with all the mud and clay being tracked everywhere.

Week 97 – Tile and Floor Progress

Slowly but surely, the hardwood floors and bathroom tile work continues.

The upstairs master is very close to completion.

img_1745

The hardwood floor installation upstairs has also started.

img_1742img_1743img_1744

The limestone outdoor patio is compete and has been grouted.

img_1741

The limestone at the front door entry way is also started.

img_1739

I’m hopeful that all the tile and floor work will be done by next week!

 

Week 96 – Floors, Tile, and More!

Hardwood floors are mostly installed in the downstair areas. Sanding and staining will happen near the very end of the project.

img_1664img_1665

The limestone lueders are also being installed in the screened patio area.

img_1666

Tile work also started in the upstairs master. I’m really excited to see how these turn out.

img_1667

They also started the cap work on the exposed concrete on the exterior of the house. The original plan was board formed concrete, but the conditions on the day of the pour (100+ degrees) made it difficult to achieve. So we are going for a smooth finish and a lot of it will be hidden by dirt and plantings anyway.

img_1668

Week 94 -Tile and Fans

Tiling work continues in the guest house. We went with a concrete tile in a starburst pattern which looks great.

img_1540img_1541

The downstairs master has the infinity drain installed and the tile work is done around the toilet room.

img_1550img_1546

Speaking of toilets, we’ve got lots in boxes!

img_1547

Fans have also been installed in rooms.

img_1545img_1544

I remembered to take a picture of the installed solar panels and all the electrical panels on the outside of the house.

img_1542img_1549

We are hoping they will start the tile work on the upstairs master this week because we really want to see the tile on the wall.