Week 94 -Tile and Fans

Tiling work continues in the guest house. We went with a concrete tile in a starburst pattern which looks great.

img_1540img_1541

The downstairs master has the infinity drain installed and the tile work is done around the toilet room.

img_1550img_1546

Speaking of toilets, we’ve got lots in boxes!

img_1547

Fans have also been installed in rooms.

img_1545img_1544

I remembered to take a picture of the installed solar panels and all the electrical panels on the outside of the house.

img_1542img_1549

We are hoping they will start the tile work on the upstairs master this week because we really want to see the tile on the wall.

Author: karcuri13

After many years wanting to start my very own hive, I'm finally taking the plunge and setting up my first urban hive in April.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s