Week 103 – Into the Home Stretch

We can finally see the light at the end of the tunnel at least for the interior. Cleanup has started in prep to finish both the concrete and hardwood floors.

The fireplace hearth was poured.

img_2049

We also have our permanent electric meter installed and the solar will be hooked in shortly so we can start getting credit from the panels.

img_2050

The guest bath tile is finished and will be grouted early next week.

img_2051img_2052

The cork floor was also installed the kitchen but is currently covered so no picture of that yet.

Next week, the driveway will hopefully get started as well as the installation of the steel planters in the auto-court.

Week 40 – Moving right along

The house has been wrapped before the exterior finishes are started.

img_2397img_2398

They have also started the installation of the flat roof material.

img_2402

Inside all in the internal systems continue to be fleshed out including electrical wiring.

img_2399

img_2403

Akash’s bathroom is coming together with the shower niche framed out.

img_2404

For the exterior, some of the bricks are onsite to start looking at the brick coursing.

img_2401

The roof/fascia color was chosen using Berridge Matte Black on the left.

IMG_0227

Things are moving right along. I expect things will slow down toward the end of December with the holidays, but good progress continues to be made.