Week 116 – Front Planters

The steel for the planters around the front steps are going in. In addition to looking good, they are necessary for safety so there is less than a three foot drop around the stairs.

img_2978img_2969img_2970img_2976

The barn door to the storage room have been painted.

img_2971

The window tinting has been applied to key windows in the master baths.

img_2974img_2973

A mirror has been added to the upstairs master closet.

img_2975

Week 109 – More Steel and Irrigation

The terrace is pretty much done and the steel bases for the railing are installed.

img_2500img_2501

All the structural steel for the floating steps for the front door entry are in place and the rest of it will be formed and poured early next week. It will be so nice to finally have steps.

img_2564

In solar news, the city passed our system and the meter has been installed. It is already pretty cool to see how our system is performing.

img_2568

The main irrigation lines are also installed allowing us to start landscaping.

Things should be wrapping up in the next month and we may move into this house yet.