Week 22 – Foundation forms removed

All the wooden forms have been removed and it now looks like we have the start of a house. Here is the view as you come up the driveway.

img_1581

Akash was very excited to run around the slab.

img_1583

Here is a view from the top terrace looking down.

img_1587

Here is a shot to show the cantilevered slab at the front of the house.

img_1591

It’s now been seven days so the concrete should be sufficiently cured to start the steel and wooden framing.

Week 21 – Pouring Foundation!

After lots of delay due to weather, the foundation finally got poured today. Due to space constrictions on the top of the site, the concrete had to be pumped up in two stages. Here is a video that shows the top pump truck and the line pipe that goes down the drive to another pump truck where the concrete was initially loaded.

The whole process took about 160 cubic yards of concrete and started at 6:00am. When we went back after lunch, the crew was wrapping up the garage and car port area. Here are a few shots of the finished product.

img_1564img_1563

This was a major milestone and we are happy to have it finally done.

Week 20 – Final site prep

We are nearing the end of the site work before the foundation is poured early next week. The cardboard formwork is in and the steel is installed over it.

img_1527

There are still a few more sections to wrap up. This is the guest suite that needs to be completed, but the beam work steel is in place and that’s the most time consuming. The horizontal slab steel goes in quickly.

img_1529

By the end of next week, we should have the concrete poured and then the framing can start.

Week 18 – Plumbing complete

We are back from a week in Orlando over the 4th of July holiday, and we visited the site this morning with the builder.

The good news is the plumbing is complete and inspected. Now that inspection has passed they can start tying in the rebar. Here is a shot from the upper terrace.

img_1481

Some random shot of the plumbing work.

img_1479

All the cardboard void forms are also onsite in preparation for the foundation pour. There is a pile up in the storage area and another large one at the bottom of the property.

img_1478

They are working this weekend and hopefully will get to a point of pouring the foundation at the end of next week.

Week 17 – Foundation Progress

We made it out to the site before the thunderstorms hit. Here is a panoramic shot from where the auto-court will be facing south.IMG_3171 copy

Here is a side by side comparison with the June 15th shot on the left and today’s on the right. You can see the plumbing work on what will be the downstairs master suite and a lot more trenches dug.

Here is a close-up of the plumbing work.

img_1414

Here is a shot where you can see the trenches with the black plastic forms that will eventually have plumbing and rebar.

img_1417

There has already been one big thunderstorm today with more in the forecast so we will have to see what that does to the schedule.

Week 16 – Dirt Excavation

We’ve had no rain in the past week so I stopped by at lunch to check on things and was greeted by a giant pile of dirt at the bottom of the lot.

img_1395

There has been lots of excavation work digging trenches for beams and plumbing and it being moved to the bottom of the site to be hauled away.

Lots of dirt is being moved at what will be the front of the house.

img_1398

You can really see the progress from the upper terrace of the lot.

img_1403

And finally, this bamboo wasn’t here last week which just goes to show you how quickly this stuff can grow. Luckily it is only in a small section of the upper terrace but we will have our work cut out for us making sure we keep this invasive plant at bay.

img_1407

Week 14 – Foundation Progress!

Most of the heavy rain occurred over the Memorial Day Holiday weekend and even though there was rain chances every day this week, we didn’t get any significant rainfall.

We now have some significant progress on setting up the forms for the foundation pour. Here is a view from the bottom of the drive.

img_1368

Here is another at an angle about half way up the drive.

img_1369

Lots of activity getting the outline of the foundation formed up.img_1377

Another shot of the work.

img_1378

In addition to the work on the foundation, the upper terrace portion has been cleared out up to the fence line.

img_1376

At the bottom of the property, the crew removed at lot of invasive species of trees and shrubs and just left the native trees.

img_1380

It is nice to see some significant progress after the past weeks of rain. Hopefully we can continue this momentum and get this foundation poured by mid-June.