We are back from a week in Orlando over the 4th of July holiday, and we visited the site this morning with the builder.
The good news is the plumbing is complete and inspected. Now that inspection has passed they can start tying in the rebar. Here is a shot from the upper terrace.
Some random shot of the plumbing work.
All the cardboard void forms are also onsite in preparation for the foundation pour. There is a pile up in the storage area and another large one at the bottom of the property.
They are working this weekend and hopefully will get to a point of pouring the foundation at the end of next week.