Week 12 – Backfill Complete

I met our architect and builder over lunch on site to discuss progress and next steps.

img_1321

The site looks much larger now that all the piles of dirt have been cleared away and the ground leveled.

img_1317

The biggest item is getting all the retaining walls completely backfilled with dirt.

img_1318

From the upper terrace, the dirt is now level with the top of the walls.

img_1319

It is also amazing how much space there is on top now that the dirt has been filled in and a good portion of the brush removed. It is also very sunny and has a completely different feel from the lower wooded portion of the lot. This will make a great area for both edible and flowering plants that just won’t work in the shaded portion of the property. I’ll also have a great place for a few beehives.

img_1323

Rain is in the forecast for the next week or so, but next steps are starting the remaining excavation work for the house foundation and start forming it up.

Week 12 – Backfill beginning

The work has begun on moving the dirt back behind the retaining walls. The trench has been filled in and the dirt moved into one central pile.

img_1307

A dirt ramp was also constructed to get to the upper terrace. This picture is the top of the ramp looking down.img_1306

The dirt is about halfway up the wall. They also cleared out a lot of the bamboo and brush on the upper terrace to allow the bobcat access to dump in the dirt.

img_1303img_1304

The next week should consist of backfilling the rest of the wall and then starting the excavation work to start building out the house foundation form.

Week 10 – Walls are finished!

Lots of progress since I went by on Sunday. We now have all the retaining walls poured. The walls around the storage shed slab are complete.

img_1283

The north wall is also poured and connected to the wall on the west side.

img_1281img_1280

I honestly wasn’t expecting these to get done so quickly but I’m not complaining. Next steps will most likely be backfilling behind the walls on the west side of the property and then starting excavating for the house foundation.

Week 10 – Continued progress on retaining walls

It is a gorgeous day in Austin so I swung by early to see if the forms had been removed after the walls were poured on Thursday. Sure enough, we now have a nice concrete wall.

img_1267

In addition to that, the north wall forms appear to be completed.

img_1264

They have also started the walls around the storage shed.

img_1269

Here is a video showing the progress on the back side of the lot.

Week 9 – Concrete poured in retaining walls

We’ve made some progress with the retaining walls and storage area foundation.

img_1256

Here is a close-up of the storage area slab.

img_1254

It appears that the wall on the north side of the property did not get poured, but it at least is formed up.

img_1252

Here is a shot of the steel inside.

img_1253

While it would have been nice to get the north wall poured as well, the west wall and the storage shed slab were the main gating factors for getting the foundation of the house started. Any progress is good progress and I’m glad this was done as rain is in the forecast for the next few days.