The work has begun on moving the dirt back behind the retaining walls. The trench has been filled in and the dirt moved into one central pile.
A dirt ramp was also constructed to get to the upper terrace. This picture is the top of the ramp looking down.
The dirt is about halfway up the wall. They also cleared out a lot of the bamboo and brush on the upper terrace to allow the bobcat access to dump in the dirt.
The next week should consist of backfilling the rest of the wall and then starting the excavation work to start building out the house foundation form.