Week 12 – Backfill beginning

The work has begun on moving the dirt back behind the retaining walls. The trench has been filled in and the dirt moved into one central pile.

img_1307

A dirt ramp was also constructed to get to the upper terrace. This picture is the top of the ramp looking down.img_1306

The dirt is about halfway up the wall. They also cleared out a lot of the bamboo and brush on the upper terrace to allow the bobcat access to dump in the dirt.

img_1303img_1304

The next week should consist of backfilling the rest of the wall and then starting the excavation work to start building out the house foundation form.

Week 10 – Walls are finished!

Lots of progress since I went by on Sunday. We now have all the retaining walls poured. The walls around the storage shed slab are complete.

img_1283

The north wall is also poured and connected to the wall on the west side.

img_1281img_1280

I honestly wasn’t expecting these to get done so quickly but I’m not complaining. Next steps will most likely be backfilling behind the walls on the west side of the property and then starting excavating for the house foundation.

Week 10 – Continued progress on retaining walls

It is a gorgeous day in Austin so I swung by early to see if the forms had been removed after the walls were poured on Thursday. Sure enough, we now have a nice concrete wall.

img_1267

In addition to that, the north wall forms appear to be completed.

img_1264

They have also started the walls around the storage shed.

img_1269

Here is a video showing the progress on the back side of the lot.

Week 9 – Concrete poured in retaining walls

We’ve made some progress with the retaining walls and storage area foundation.

img_1256

Here is a close-up of the storage area slab.

img_1254

It appears that the wall on the north side of the property did not get poured, but it at least is formed up.

img_1252

Here is a shot of the steel inside.

img_1253

While it would have been nice to get the north wall poured as well, the west wall and the storage shed slab were the main gating factors for getting the foundation of the house started. Any progress is good progress and I’m glad this was done as rain is in the forecast for the next few days.

Week 9 – Walls getting closer

It appears the rain last week prevented the walls from being poured. There is now a large trench from the back of the lot which I’m assuming is there to help the water drain. 

Here is the north wall with the water proofing and drainage system. 
Here is the west wall with the final form on meaning the steel was inspected. This will be the storage room foundation that ties into the retaining wall. The trench leads up to this area so I’m assuming this back area was too wet to get formed up for the pour. Another shot of the west wall. Shot of trench from storage area looking toward the front of the lot.