Week 110 – Bridge Prep

The existing bridge over the dry creek bed is being removed and replaced to allow water to flow more freely during large rain events. The initial work has been started to pour the footings and then the bridge will be removed.

img_2599

Landscaping and grading continue. The planters have been filled with rock for drainage.

img_2602

The upper terrace continues to be graded and soil brought in. Holes have been dug for the fruit trees.

img_2605

Here is a shot showing the bed around the back of the garage where the citrus trees will go.

img_2607

The screen door has been installed on the patio.

img_2609

The wine cooler has also been installed in the pantry which was the last major appliance.

img_2608

We may get some much needed rain today, but next week should be dry and will allow the entry steps to be poured as well as the bridge.

 

Week 109 – More Steel and Irrigation

The terrace is pretty much done and the steel bases for the railing are installed.

img_2500img_2501

All the structural steel for the floating steps for the front door entry are in place and the rest of it will be formed and poured early next week. It will be so nice to finally have steps.

img_2564

In solar news, the city passed our system and the meter has been installed. It is already pretty cool to see how our system is performing.

img_2568

The main irrigation lines are also installed allowing us to start landscaping.

Things should be wrapping up in the next month and we may move into this house yet.

Week 108 – Steel Work

The steel work has started in the house for both the interior and exterior. On the inside, the fireplace wrapping is installed.

img_2360

The staircase railing has also started.

img_2363

On the exterior, the planters and trellis installing on the roof top deck has also started.

img_2366img_2368

In addition, lots of other general progress. The garage door has been installed.

img_2306

The footing for the staircase leading up to the front door has also started.

img_2307

We should be tracking for completion no later than end of April. We can’t wait to move in!

Week 106 – Bathroom Glass

The upper part of the driveway has cured and looks great.

img_2276

The wood is being installed over the fireplace.

img_2279

All the glass has been installed in the bathrooms.

img_2277img_2283img_2281img_2282img_2284

The stove finally arrived has been installed.

img_2280

It also looks like the garage door has been installed but since it was left open I didn’t want to try closing it in case it wasn’t final yet.

The wood floors are also being prepped for finishing so that will start next week as well.

Week 105 – Appliances

We have been in India for the past few weeks so it was fun to see all the progress made while out of the country.

We arrived today to find the driveway pour started.

img_2146

After navigating around pour, we found all the steel planters installed in the auto-court.

The front door hardware has been installed.

img_2156

The wallpaper has been applied in the powder room.

Kitchen appliances have been installed with the exception of the stove which is currently lost in transit somewhere.

img_2153img_2154

Mirrors have been installed in the bathrooms.

img_2155

The outdoor kitchen appliances have also been installed.

img_2152

Things are progressing nicely and we will hopefully be moving soon.

Week 103 – Into the Home Stretch

We can finally see the light at the end of the tunnel at least for the interior. Cleanup has started in prep to finish both the concrete and hardwood floors.

The fireplace hearth was poured.

img_2049

We also have our permanent electric meter installed and the solar will be hooked in shortly so we can start getting credit from the panels.

img_2050

The guest bath tile is finished and will be grouted early next week.

img_2051img_2052

The cork floor was also installed the kitchen but is currently covered so no picture of that yet.

Next week, the driveway will hopefully get started as well as the installation of the steel planters in the auto-court.